Current Projects

The mission of the Sheridan County Engineer's Office is to design, build, and maintain the safest, most efficient roadway network possible for the citizens of Sheridan County Wyoming.
Thanks for visiting our web site --- your best source for public information about the County roadway system.

PROJECTS CURRENTLY UNDER CONSTRUCTION

PROJECTS UPDATE


January 4, 2008

Half Way Lane Bridge

 Installation of the new bridge is well under way with an anticipated substantial completion date of March 1, 2008 and a final completion date of March 31, 2008. The project is on schedule and in budget.

Cottonwood Bridge

The damaged bridge has been removed and the area dressed up. Western Water Consultants has completed Phase 1, which included drilling, lab testing and surveying. They are currently designing the foundation, reviewing the hydrology, and researching bridge selection.

Soldier Creek Rd

Barker Construction and Lewis Holding Inc. were contracted to haul, place and shape approximately 10,000 cubic yards of material to reconstruct the road to the west of Dr. Tim Scott's approach in order to improve the line of sight from this approach. This project was completed on 12/20/07 at a cost of $68,157.50. Due to the onset of winter, final grading of the roadway, shaping and seeding of the side slopes and the rebuilding of the fence will be postponed until spring. At that time the SR&B crew will finish the remaining work. The County Engineer's office has completed a design for the reconstruction of the roadway in the vicinity of the VA water treatment plant. This project will require approximately 6,500 cubic yards of material and will be scheduled for commencement in the spring of 2008.     

Passaic Rd 

The condition of Passaic Road was checked at the end of November to determine if the treatment with bentonite and chloride was effective. The first six miles (from the highway to the junction with Buffalo Creek) are in very good shape with only a little scrubbing on a couple of the sharper corners. The second six miles (from the junction with Buffalo Creek to the north) are showing some raveling in several locations. Additional clay material still needs to be added to the road material to help hold it together and to help the chloride work.

Wild Horse - South Prong Roads - Upper Powder River Rd

Wild Horse Road was checked at the end of November also. It is holding together quite well. Some potholes are starting to develop, but overall the road is in excellent condition. There is one spot at the end of the one mile that was stabilized that is coming apart.  South Prong road is in excellent condition with only a few potholes starting to develop.

Upper Powder River Road will be scheduled for treatment with bentonite and chloride in 2008.

Mydland Rd -  West 5th Street -  Kentucky Ave. -  Dry Ranch Road

Our department has asked Randall Engineering Surveys to provide the needed description on West 5th and Dry Ranch Road. The status of this project is unchanged at this time. 

KROE Lane - East Ridge Rd

The City is working on the paper work to get these roads transferred to the City. Prestfeldt has been contracted jointly by the County and the City to prepare a description of the road. The status of this project is unchanged at this time.


SLIB GRANT 2005

Lower Prairie Dog

Linear grading has been completed on Lower Prairie Dog from Coutant Creek Road to the railroad crossing. The final hauling and placing of gravel on this portion of the road and treatment with chloride will be scheduled for the spring of 2008.

Badger Creek Road 

This road will be scheduled for treatment with chloride in 2008.

Lower Powder River Road

Pro Stock Fencing has completed the ROW fence on both sides of the roadway from the north end of the second section of the realignment to the north end of the first section. The contractor should complete the fence on the first section of the realignment in the next three weeks. The bentonite and chloride that was applied to the first 6.5 miles in September is holding up very well considering the amount of traffic that this road is experiencing. The chloride treatment on the realignment section is developing more potholes and starting to come apart in a couple of places. This may be due to the fact that this was the first treatment with chloride and Pee Gee gravel has a low PI.  The County Road & Bridge personnel started hauling gravel from the Pee Gee Pit on November 19, 2007 using six trucks. They started at approximately mile marker 6.5, proceeding to the north. As of December 20, 2007, a six-inch lift of gravel has been placed on approximately seven miles of road.  They started hauling and placing gravel again on January 2, 2008 with four trucks.

Thompson Creek Rd

Status of this project remains unchanged. The Clear Creek Bridge will have to be replaced before we can move forward.

S R & Buffalo Creek Road

The status of this project is unchanged.

ULM Road

Tietjen gravel was hauled and placed on the road from Clearmont to Ulm. Another lift (3") of gravel is needed on this road plus bentonite will need to be incorporated into the road material before chloride is applied. The bentonite and chloride work will be scheduled along with the work on Upper Powder River road.


CMAQ Grant 2005

Beatty Gulch & Beatty Spur

The work to satisfy the grant requirements has been completed and the final draw down request has been submitted. The SR&B crew has also hauled and placed pit run material on approximately two miles of the dry weather portion of the Beatty Gulch road to upgrade this portion of the road. This work was not part of the grant project. 

  

SLIB Grant Projects 2006

Dutch Creek Road

Upgrading of this road was approved in the 2006 SLIB grant. Several culverts have been replaced and/or extended and the ditches have been pulled and the road reshaped. The first lift of gravel has been placed on approximately 13 miles of road. Dust control is also included in this project and will be scheduled for 2008. Additional grading and culvert work will be performed in the spring. A contractor will be utilized to perform the grading work and SR&B will perform the culvert work.

Dow Prong Road

The culvert work and the cattle guard replacement added to the contract with Smith Contracting have been completed. We have been utilizing eight to twelve trucks to haul and place gravel from the Kusel Pit on this road.   A six-inch lift has been completed on approximately six miles. Dust control is included in the grant and will be scheduled for 2008. The County also plans to perform additional grading and culvert work on a portion of this road. A contractor will be utilized to perform the grading work in conjunction with the work on Dutch Creek and SR&B will perform the culvert work.

 Lower Prairie Dog

The bid proposal for the realignment of 1.4 miles of roadway is scheduled for advertisement on January 9, 2008 with a projected date of February 5, 2008 for awarding the contract.

SR - Buffalo Creek Road

The status of this project is unchanged.

Clear Creek Bridge

Replacement of this bridge was approved in the 2006 SLIB grant. Western Water Consultants has finished its study of the geology for the bridge abutments.

Downer Addition County Road 80

A grant has been approved to cover a 50-50 match on a $1,000,000.00 road project. Entech Inc. was hired to evaluate drainage problems and complete the road design. Design work is currently underway. 


CMAQ Grant 2006

Murphy Gulch Rd

This project includes linear grading, placing crushed gravel on approximately 6 miles of road and treating with chloride. Culvert work and linear grading will be scheduled for the spring of 2008.  Gravel hauling and placing along with chloride treatment will be scheduled after the linear grading has been completed. This work will need to be completed by September 30, 2008 to satisfy the grant requirements.

Wolf Creek Road

Magnesium Chloride was applied to 4.0 miles of this road.

Beaver Creek Road

Ten miles of this road was treated with Magnesium Chloride.


GRAVEL PITS 

Rhodes Pit

Design of a temporary bridge to access the pit is underway.  This is part of the work that is being performed by Western Water Consultants. This bridge could possibly be used for a detour to the Thompson Creek Road while the Clear Creek Bridge is being replaced.

Kusel Pit No. 2

We are currently preparing a permit for Pits No. 3 and 4.   Crushed gravel from Pit No.2, which is nearly depleted, is currently being hauled to Dutch Creek and Dow Prong.

Pee Gee Pit

Gravel from this pit is currently being hauled and placed on the Lower Powder River road.

Bocek Pit

Sheridan Road and Bridge has indicated that they want to keep this pit active for a source of pit run scoria. The necessary permits will be obtained to keep this pit active.

Dewey Pit No. 4

Sheridan County entered into an hourly agreement with P.E.Grosch Construction Inc. to haul approximately 50,000 cubic yards of stockpiled overburden material to reclaim the pit disturbance. Grosch Construction completed this project on 1/2/2008. The landowner, Carlton Dewey, requested that a stockpile of fines be left in the pit for his use at a later date. There is still a stockpile of crushed gravel in the pit that will be used on Lower Prairie Dog Road. The engineering department in the near future will be evaluating the financial feasibility of crushing more gravel from this pit.

 
If you would like more information on the projects you may call the Sheridan County Engineering Office at (307) 674-2920.
designed by: Wyolution